Predictive Change Control (CCB) vs Agile Backlog Prioritization (PO)
10-Second Exam Rule:
Predictive project scope change -> Assess impact first, then submit formal Change Request to CCB. Agile/Scrum request -> Protect current Sprint and route to Product Owner for Product Backlog prioritization.
Side-by-Side Decision Matrix
| Dimension | Predictive (Waterfall) | Agile (Scrum) |
|---|---|---|
| Change Authority | Change Control Board (CCB) | Product Owner (Product Backlog) |
| First Step on Request | Assess impact across constraints | Direct stakeholder to Product Owner |
| Mid-Execution Protection | No work before CCB approval | Active Sprint Backlog stays shielded |
Pick Predictive Change Control (CCB) when…
- Project uses a predictive (waterfall) lifecycle with approved scope, schedule, and cost baselines.
- Stakeholder requests an out-of-scope addition after execution begins.
Pick Agile Backlog Prioritization (PO) when…
- Project uses Scrum/Agile iterations with a Product Owner and prioritized Product Backlog.
- Stakeholder asks a developer mid-sprint to add or swap a feature.
Primary exam distractor trap
Selecting 'submit a Change Request to the CCB' on a Scrum question, or selecting 'add it immediately to the active sprint'—both violate core PMI governance.
Test if you can spot the rule under pressure
Mid-way through Sprint 4 of a Scrum project, a VP asks a developer to slip in a new report before Friday. What should the PM do?
Practice this exact scenario inside the Pass Workspace