PMP Exam-Day Cheat Sheet
Distilled rules of thumb and the exact exam traps that separate borderline candidates from those who clear 70%.
The PMI Mindset Rules (Solves ~60% of PMP Questions)
Top Exam Traps to Avoid
- Escalating to the sponsor or HR before assessing and collaborating directly.
- Implementing a predictive scope change without CCB approval—or forcing a CCB onto a pure Scrum team.
- Putting an event that ALREADY happened into the Risk Register instead of the Issue Log.
Exam-Day Rules of Thumb
- Assess/Analyze impact FIRST before taking action or escalating.
- Predictive change = Impact Analysis -> CCB Change Request. Agile change = Route to Product Owner -> Product Backlog.
- CPI/SPI > 1.0 = Favorable (under budget / ahead of schedule); < 1.0 = Unfavorable.
Predictive vs Agile Decision Rules on PMP
| Situation | Predictive (Waterfall) | Agile (Scrum) |
|---|---|---|
| Stakeholder asks for new feature | Assess impact -> Submit CR to CCB | Route to Product Owner -> Product Backlog |
| Known risk occurs | Issue Log -> Contingency Reserve | Raise impediment -> Adapt in Sprint/Backlog |
| Team conflict | Coach + Collaborate / Problem Solve | Facilitate + Revisit Team Charter |