PMP Free Practice Test & Weak-Domain Diagnostic
Answer 3 realistic PMP scenario questions below (no signup required) to get your blueprint-weighted Readiness Score against the 70% passing bar.
Process (50% blueprint weight)
During the execution phase of a predictive infrastructure project, a key operations manager asks you in a hallway conversation to add an automated failover dashboard that is not in the approved scope baseline. What should you do FIRST?
--Pass 70%
What’s Tested Across PMP Domains
Domain 1: People42% Weight
Servant leadership, conflict resolution, coaching teams, removing impediments, stakeholder engagement.
Domain 2: Process50% Weight
Integrated change control, risk vs issue management, Agile/Hybrid ceremonies, EVM (CPI/SPI), procurement.
Domain 3: Business Environment8% Weight
Compliance, benefits realization, organizational change management, value delivery.